Green Giraffe was mandated by EMF, the joint venture between EDF EN and DONG Energy, to assist them on modelling tasks during the bidding process under the French offshore wind tender
Project highlights
- 5 offshore zones with up to 3,000 MW of capacity open to the tender
- Tender is the path selected by France to reach goal of 6 GW of offshore wind capacity by 2020
- Tender criteria included level of tariff requested by bidders, as well as quality of industrial proposal and environmental impact
Tender highlights
- EMF bid in 4 of the 5 zones
- 4 zones allocated in April 2012
- EMF won 3 of them, for total capacity of 1,428 MW